South Jerrabomberra – Construction Update – November 2020

  • South Jerrabomberra – Construction Update – November 2020 image

The beautiful landscape at South Jerrabomberra is taking shape with street trees now planted along Environa Drive and throughout Stage 1A. Grass has also been planted and is beginning to grow along the street verges.

The concrete deck on the bridge across Jerrabomberra Creek has been poured and works are now continuing on the road approaches and bridge railings. The bridge will allow for two lanes of traffic, on road cycling and a shared pedestrian path.

The concrete works on the low-level water reservoir are now complete and the reservoir has been filled with water to commence the testing process. This reservoir will supply water to homes across the first two release areas.

Work in the sewer pump station is now well underway with the concrete emergency storage tank under construction.

An unseasonably wet Spring has seen some minor delays on site, however we are continuing to work towards subdivision certificates and registration of titles for settlement within Release Area 1 by mid-2021.

Landscaping at South Jerrabomberra