South Jerrabomberra – Construction Update – October 2020
There has been considerable progress on works across South Jerrabomberra in recent weeks.
Construction of Environa Drive remains on track to be completed early next year. The concrete beams have now been installed on the bridge over Jerrabomberra Creek and the trees that will line the road have been ordered.
Asphalt has now been laid across roads in Stage 1A and the first street trees have been planted.
Work on the low- and high-level reservoirs continues and the sewer pump station with in-ground pipework has progressed.
Village is continuing to work towards subdivision certificates and registration of titles for settlement within Release Area 1 by mid-2021.
Take a look at the bridge beam installation:
Take a look at the asphalt being laid: