Realm at Austral – May Construction Update

Realm Stage 1, 70-100 Seventeenth Ave 

Final asphalting and line marking is complete. Thank you for your patience whilst these works were completed.

Realm stage 2 (81 Lots) 75-115 Eighteenth Ave Austral

The Construction Certificate has been approved by Liverpool Council. The contract has been signed for the civil works, with Western Earthmoving to construct the 81 Lots and temporary dam. Works will commence mid May 2019 and are expected to complete in February 2020 subject to weather and delays. Registration is anticipated in April 2020 with settlements shortly thereafter.

Realm Stage 1 & 3,  35 – 55 Eighteenth Ave

NBN Co. are currently laying optic fibre cable to these development stages. Stage 1 is anticipated to be completed by June 2019 with phase 2 expected to be complete by July 2019. We will send further updates as soon as more information becomes available.