Yarraman - Construction Update - September

19 September 2018

Yarraman - Construction Update - September

Overall the site is progressing well.  The rock beaching along Mile Creek has been completed with the Mile Creek park area starting to take shape.  We have built a wall to screen the industrial area on the northern side of the creek corridor which looks great.  Although not required from an acoustic perspective its great we could work with our neighbours to provide such a positive outcome for the new community.

The Sky Rail has now been completed with the upgrade making transport move more efficiently.  Yarraman Village is certainly in a great location for easy access to Melbourne City and the inner suburbs.

Latest release 

We understand many of you have been waiting for our next release at Yarraman being Stages 5 and 6.  These will be available shortly so if you are interested or know someone who is please contact Lisa Wood on 0476 807 465 for more details! 

We are offering a $500 voucher for family and friend referrals so if you have a friend looking for a new home please make sure they provide your name to Lisa when they contact us.

 

Stage 1 (lots 10 - 41)

Although Stage 1 is looking great and the homes are taking shape, JG King (Stage 1 builder) continues to be behind schedule.  We are working with them to ensure your home is completed to the highest standard.  We will provide each home owner in Stage 1 with a personal update in the coming weeks.

Stage 2-3 (lots 42- 80)

Civil works have been completed on these stages with our new builder (Level 10) having commenced construction.  Its great to see that Level 10 are 3 weeks ahead of schedule and are on track to deliver your home to you by the middle of next year.  We will provide further updates throughout the building process.

 

Stage 4 (lots 81 - 106)

Civil works on this stage are expected to be completed by the end of September with Level 10 also appointed as the builder for this stage.  Homes in this stage are on track for delivery by the third quarter of next year however we will continue to keep you updated as the build progresses.