Yarraman - Construction Update - July

3 July 2018

Yarraman - Construction Update - July

Stage 1

Construction is progressing well onsite and we can advise that:

 

Lots 10 - 14 : The roof has been installed and cladding will be fitted externally over the next few weeks.  These townhouses are expected to be at ‘lock up stage’ this month.

Lots 15 - 22: Plaster will be installed internally with cladding to be fitted externally over the next two weeks.

Lots 23 - 27: Frames have been completed to the lower storey with the top storey expected to be complete within a fortnight.

Lots 28 - 33: Plaster will be installed internally this month along with the kitchens.

Lots 34 - 41: Internal fit out is nearing completion with painting commencing this week.

Stages 2 - 4 : Civil works almost complete roads are tarred builder to commence on site early August.

Stages 5 - 6 : Civil works tracking to program.