Yarraman - Construction Update - July
Yarraman - Construction Update - July
Stage 1
Construction is progressing well onsite and we can advise that:
Lots 10 - 14 : The roof has been installed and cladding will be fitted externally over the next few weeks. These townhouses are expected to be at ‘lock up stage’ this month.
Lots 15 - 22: Plaster will be installed internally with cladding to be fitted externally over the next two weeks.
Lots 23 - 27: Frames have been completed to the lower storey with the top storey expected to be complete within a fortnight.
Lots 28 - 33: Plaster will be installed internally this month along with the kitchens.
Lots 34 - 41: Internal fit out is nearing completion with painting commencing this week.
Stages 2 - 4 : Civil works almost complete roads are tarred builder to commence on site early August.
Stages 5 - 6 : Civil works tracking to program.