The Village at Corrimal - Construction Update - December

7 December 2018

The basement slab on the eastern Block B is complete and formwork for the ground floor slab is progressing. Half the external basement walls have been installed and poured. We are scheduling completion of the ground floor slab prior to Christmas.

The western Block A basement slab is progressing a little slower due to some bad weather but we are scheduling to have the basement slab complete and ground floor formwork started prior to Christmas.

Next week will be an exciting week on site as we have the erection of the tower crane that will help with construction progress.

We have had a very productive year with over 40% of the project now sold!  So we are going to be taking a well earned break over Christmas. Gabrielle’s last day for the year will be Saturday 15 December, however the office on Railway street will remain open until close of business Friday 21 December 2018.  The office will re-open on Wednesday 2 January 2019. We wish everyone a safe and happy holiday period!

 

Villas at corrimal construction

Villas at Corrimal team Villas at corrimal construction