South Jerrabomberra - Construction Update - March 2021

7 June 2021

Despite the recent rain, construction is progressing rapidly at South Jerrabomberra, which ensured that  our construction program met our Easter target, to keep settlement timeframes on track. 

Overall, despite weather challenges, the construction of house and land packages is also progressing quickly with 30 homes now under construction and significant progress since our last update. 

Some of our land buyers will have started to receive communication about valuations and settlements. We are also following up with phone calls to ensure we are able to reach everyone with the next steps for land settlements.  

Overall estate update 

Environa Drive, which is the main entry road into the estate, has completed asphalt from the estate entry all the way to the location of the Regional Sports Centre intersection. Further progression of this road (up to North Tralee, which is the commercial component of South Jerrabomberra), will be progressed next week. 

We have lodged the Subdivision Certificate with council and are expecting to receive the approval very soon. Once we receive the Subdivision Certificate, we will lodge with Land Registry Services to have titles registered.

Approximate settlement timelines 

To assist you in planning ahead for your finance and accommodation requirements for 2021, we are pleased to report the following outline of settlements. These timelines are a guide only at this stage but can be used to make any arrangements you need to. We will be in contact closer to the time to provide you with further information. 

1A – from 26 May and concluding 15 June 2021 
AI – late August 
1B1 – from 26 May and concluding 15 June 2021 for AJ/AP 
1B2 – late July/August 
1C – late August/early September