South Jerrabomberra - Construction Update - February 2021

1 March 2021

Both housing and civil construction at South Jerrabomberra are progressing at great speed and we would to thank everyone who joined us last Saturday to see the progress first-hand.

The South Jerrabomberra Residents' BBQ was held on Saturday 20 February to allow you to experience the estate from the high-level reservoir. We wanted to give you a view like no other! What a terrific day it was weather wise – we enjoyed the opportunity to share our progress with you and answer any questions you may have. Stay tuned for more resident events like this!

We have just uploaded the event photos to our Facebook page.

Housing construction

If you attended on the weekend, you would have seen the progress of housing construction in Section AI. We have been very lucky with the weather recently which has allowed us to continuously progress.

Specifically, we now have 21 homes that have their slabs poured and 18 of these homes have completed frames - a further 12 have had trusses installed. Most homes now have windows and 6 roofs are completely finished. We will be pouring 3 more slabs next Tuesday. 

Civil construction

The implementation of infrastructure services are now substantially complete. This includes the high-level reservoir concrete works (which you may have seen on the weekend), sewer, water, and utilities pipework now run all the way from Jerrabomberra Creek to the South Jerrabomberra Estate.

Envriona Drive continues to progress. The main road from the South Jerrabomberra Estate to Jerrabomberra Creek have shared concrete paths and gravel now continues the entire length of the road. Asphalt within the residential areas of the first release is complete and final landscaping is underway.

South Jerrabomberra Construction Update - February 2021